Announcement from PSEG: Weekly Construction Report

News & Info 2026 Posted on March 03, 2026

Announcement from PSEG
The Southampton to Deerfield (SHDF) Transmission Project 
 

Week of February 23, 2026
Activities suspended due to inclement weather

Week of March 2, 2026
Anticipated activities include:

  • Continue splice vault 2 installation activities (North Main Street, south of CR39A, road closure during vault installation)
  • Begin splice vault 3 installation activities (North Main Street, north of CR39A, road closure during vault installation)
  • Continuing test pitting and survey activities
  • Continue installation of cable trays at substation
  • Continue foundation preparations at substation

Week of March 9, 2026
Anticipated activities include:

  • Complete conduit installation activities (Willow Street closed to thru traffic)
  • Begin conduit installation activities (North Main Street, north of CR 39A)
  • Continue conduit installation activities (North Main Street, south of CR 39A)
  • Begin splice vault 4 installation activities (North Main Street, road closure between Deweil Road and North Sea Mecox Road during vault installation)
  • Begin splice vault 5 installation activities (North Sea Mecox Road, road closure between North Main Street and David White’s Lane during vault installation)
  • Continue test pitting and surveying activities
  • Continue installation of cable trays at the substation.
  • Continue foundation preparations at the substation.
 
Project In-Service: Anticipated December 2026.
For questions about the SHDF Project, call or text 631-237-7196
Email: info@southampton2deerfield.com